Geometric Design of Upper Cisokan Hydroelectric Power Plant Access Road with AutoCAD® Civil 3D (STA 3+000 - STA. 4+800)
DOI:
https://doi.org/10.53866/jimi.v2i5.200Keywords:
Access Road, AutoCAD® Civil 3D, Horizontal Alignment, Vertical AlignmentAbstract
The project to upgrade the access road to the Cisokan hydroelectric power plant and handle landslides is known as the Upper Cisokan Hydroelectric Power Plant Access Road Project. This access road has been a plan and completed build by PT. Pembangunan Perumahan (Persero) Tbk in 2019. There are several geometric alignments of the road with sharp curves. In this paper, the author intends to make a geometric plan for a new road in an area of STA. 3+000 – STA. 4+800. Planning is carried out using the AutoCAD® Civil 3D application for more effective and efficient results. The research method used is the Qualitative Method. The data source is obtained from the project data of the contractor, an access road to the Upper Cisokan hydroelectric power plant, and a reference to the Road Geometric Design Guidelines in 2021. Contour data is obtained from Google Earth® and processed using the Global Mapper® application. Planning is carried out by determining the design criteria of the road under review. Then the design criteria are used as a reference in making horizontal alignments, vertical alignments, superelevation, road assemblies, and corridor planning. The results of the planning obtained seven curves of horizontal and five curves of vertical. Furthermore, the AutoCAD® Civil 3D application is more effective and efficient because the process is relatively fast and easy, and changes to an item can be directly connected to all items.
References
Al-Sahili, K., & Dwaikat, M. (2019). Modeling geometric design consistency and road safety for two-lane rural highways in the west bank, Palestine. Arabian Journal for Science and Engineering, 44(5), 4895-4909.
Anwari, M. (2022). Mapping of The Classification of Road Pavement in Berangas Village, Alalak District. Prosiding Pengembangan Masyarakat Mandiri Berkemajuan Muhammadiyah (Bamara-Mu), 2(1), 271-274.
Arrang, A. T., Tarru, R. O., Alik, A., Basri, H., & Miri, G. (2022). Tinjauan Desain Tikungan Ruas Bua–Batas Toraja Utara untuk Peningkatan Layanan Jalan. Journal Dynamic Saint, 7(1), 19-26.
Aryal, P. (2020). Optimization of geometric road design for autonomous vehicle. Degree Project In Structural Engineering And Bridges, 23.
Chakole, H., & Wadhai, P. J. (2022). A Review on The comparison of geometric design using Civil 3D software and manual method. ResearchGate, 117-118.
Choir, I. R., Iskandar, J., Parikesit, P., Partasasmita, R., Husodo, T. K., & Megantara, E. N. (2018). The local management and sustainability of swidden farming in the Villages of Bojongsalam and Sukaresmi, Upper Cisokan Watershed, West Java, Indonesia. Biodiversitas Journal of Biological Diversity, 54-1065.
Erdiwansyah, E., Mahidin, M., Husin, H., Nasaruddin, N., Khairil, K., Zaki, M., & Jalaluddin, J. (2021). International Journal of Coal Science & Technology. International Journal of Coal Science & Technology, 483-499.
Gaikawad, P., & Ghodmare, S. D. (2020). A Review-Geometric Design of Highway with the Help of Autocad Civil 3D. International Journal for Research in Applied Science and Engineering Technology, 8(5).
Hasan, A. N., Firdaus, M. R., Sundara, A., & Astor, Y. (2020). Geometric Design of Access Road Towards the Bailey Mountain Bentang Bridge. In International Seminar of Science and Applied Technology. Atlantis Press., 283-289.
Hui, N., Saxe, S., Roorda, M., Hess, P., & Miller, E. J. (2018). Measuring the completeness of complete streets. Transport reviews, 73-95.
Isradi, M., Rachmansyah, L., Rifai, A.I., Mufhidin, A., Prasetijo, J., (2022), Analysis of Damage for Flexible and Rigid Pavement Using Pavement Condition Index (PCI) and Bina Marga Methods (Case Study: Narogong Cileungsi – Bantar Gebang Highway), JTI International Journal of Transportation and Infrastructure Vol 6 No 1, pp 30-37
Kazemiroodsari, H., & Kamat, A. (2021). Geometric Design Project for First Year Civil Engineering Students. In 2021 First-Year Engineering Experience, 2-9.
Mandal, M., Pawade, P., & Sandel, P. (2019). Geometric design of highway using Civil 3D. International Journal of Advance Research, Ideas and Innovations in Technology, 5(3).
Pandey, S., Atul, E., & Bajpai, Y. (2019). Designing And Proposing A Flyover Road Using Autocad Civil 3d Software. Planning, 5.
Putri, E. E., Nanda, M. L., & Aminsyah, M. (2021). Perencanaan Geometrik Jalan Menggunakan Autocad Civil 3D Studi Kasus Jalan Duku–Sicincin (Sta 0+ 000–Sta 2+ 700) Provinsi Sumatera Barat. Jurnal Rekayasa Sipil (JRS-Unand), 17(2), 140-152.
Rahayu, E. W., Febrianti, B. S., & Khadafi, M. (2021). Kajian Infrastruktur Jalan Lingkungan Permukiman Desa Montong Gamang. Jurnal Sangkareang Mataram, 34-39.
Raji, S. A., Zava, A., Jirgba, K., & Osunkunle, A. B. (2017). Geometric Design of a Highway Using Autocad Civil 3d. Journal of Multidisciplinary Engineering Science and Technology (JMEST), 4-6.
Rifai, A. I., Hadiwardoyo, S. P., Correia, A. G., & Pereira, P. A. (2016). Genetic Algorithm Applied for Optimization of Pavement Maintenance under Overload Traffic: Case Study Indonesia National Highway. Applied Mechanics and Materials (Vol. 845), 369-378.
Rifai, A. I., Hadiwardoyo, S. P., Correia, A. G., Pereira, P., & Cortez, P. (2015). The data mining applied for the prediction of highway roughness due to overloaded trucks. International Journal of Technology, 6(5), 751-761.
Rifai, A. I., Latief, Y., & Rianti, L. S. (2018). Data mining applied for earthworks optimisation of a toll road construction project. In MATEC Web of Conferences (Vol. 195, p. 04019). EDP Sciences., 1.
Rifai, A. I., Surgiarti, Y. A., Isradi, M., & Mufhidin, A. (2021). Analysis of Road Performance and the impact of Development in Pasar Minggu, Jakarta: Case Study of Jalan Lenteng Agung-Tanjung Barat. ADRI International Journal of Civil Engineering, 6(1), 68-74.
Shamin, N., & Demak, N. A. (2019). Evaluasi Tingkat Penerangan Jalan Umum (PJU) Di Kota Gorontalo (Studi Kasus: Ruas Jalan Prof. Dr. Jhon Katili). RADIAL: Jurnal Peradaban Sains, Rekayasa dan Teknologi, 44-61.
Sugiharto, A. (2018). PLTMH sebagai alternatif pembangkit listrik ramah lingkungan. Swara Patra: Majalah ilmiah PPSDM Migas, 107-118.
Turk, Y. (2019). Forest Road Design with Cad Software: A Case Study in the Western Black Sea Region of Turkey. Fresenius Environmental Bulletin, 28(3), 1743-1751.
Widari, L. A., Akbar, S. J., & Fajar, R. (2021). Analisis Tingkat Pelayanan Jalan (Studi Kasus Jalan Medan–Banda Aceh km 254+ 800 sd km 256+ 700). Teras Jurnal, 5(2).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2022 Adlin Arifin, Andri Irfan Rifai, Muhammad Rizal S

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.