ANALISA OPTIMASI WAKTU DAN BIAYA DENGAN MENGGUNAKAN METODE DURATION COST TRADE OFF PADA PROYEK PEMBANGUNAN PENANGANAN ROB ERETAN KABUPATEN INDRAMAYU JAWA BARAT

Authors

  • Agung Sutarto Universitas Negeri Semarang
  • Kharismawan Irfan Fauzy Universitas Negeri Semarang

DOI:

https://doi.org/10.53866/jimi.v3i1.101

Keywords:

Time Cost Trade Off Method, Additional Labor and Working Hours, Risk of Delay

Abstract

In the planning of construction work, various things can happen in the implementation of construction projects which can cause an increase in implementation time so that the completion of the project becomes late. Delays in project work can be anticipated by accelerating implementation, but still paying attention to cost and quality factors. This study analyzed the acceleration of project duration in the implementation of the Indramayu Regency Eretan ROB Handling Development Project with the addition of working hours (overtime) which varied from 1 hour of overtime to 3 hours of overtime and with the addition of manpower using the time cost trade off method. From the normal cost of Rp. 20,778,458,753 and a duration of 307 days with the analysis of the time cost trade off method, it was concluded that the most efficient addition of overtime hours was the addition of 3 hours of overtime with a cost of Rp. 20,275,217,792 for a duration of 244 days and for the most efficient addition of labor was the addition of manpower to 3 hours of overtime work at a cost of Rp. 20,295,750,961 durations of 244. So that the results of the most efficient analysis are by adding 3 hours of overtime work with a difference from the normal cost of Rp. 503,240,961 and with a difference in duration of 63 days from the normal duration.

References

A. Rani, H. (2016). Manajemen Proyek Konstruksi (Susanto Haris, Ed.; 1st ed., Vol. 1). CV. Budi Utama.

Dipohusodo, I. (1996). Manajemen Proyek dan Konstruksi (1st ed.). Kanisius.

Fardila, D., & Adawyah, N. R. (2021). Optimasi Biaya dan Waktu Proyek Konstruksi dengan Lembur dan Penambahan Tenaga Kerja. INERSIA: LN formasi Dan Ekspose Hasil Riset Teknik Sipil dan Arsitektur, 17(1), 35-46.https://doi.org/10.21831/inersia.v17i1.39499

Haedar Ali, T. (1990). Prinsip-Prinsip Network Planning (3rd ed.). Gramedia.

Handayani, F. S., Sulistiofanny, R. A. I., & Sugiyarto, S. (2017). Penerapan Time Cost Trade Off Dalam Optimalisasi Biaya dan Waktu Dengan Penambahan Shift Kerja dan Kapasitas Alat (Studi Kasus Proyek Pembangunan Jalan Tol Solo-Semarang, Ruas Bawen-Solo Seksi Ii). Matriks Teknik Sipil, 5(2).

Husen, A. (2010). Manajemen Proyek (Dwi Pabantini, Ed.). CV. Andi Offset.

Maharany, L. (n.d.). Fajarwati. 2006.“Analisis Optimasi Percepatan Durasi Proyek dengan Metode Least Cost Analysis.” Utilitas, 14(1), 113–130.

Priyo, M., & Paridi, M. R. A. (2018). Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Konstruksi Pembangunan Gedung Olah Raga (GOR). Semesta Teknika, 21(1), 72–84. https://doi.org/10.18196/st.211213

Putra, R. A. (2020). Analisa Perbandingan Percepatan Pelaksanaan Proyek dengan Penambahan Tenaga Kerja dan Penambahan Waktu Kerja dengan Metode Time Cost Trade Off pada Proyek Pembangunan Balai Karantina Pertanian Jawa Tengah.

Sekaran, U., & Bougie, R. (2016). Research methods for business: A skill building approach. John Wiley & Sons.

Setiawan, I., Siboro, I., & Faisyal, M. (2021). Optimasi Waktu dan Biaya Proyek Menggunakan Metode Time Cost Trade Off (TCTO): Time and Cost Project Optimization Using the Time Cost Trade Off (TCTO) Method. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 3(2), 114–128. https://doi.org/10.36277/transukma.v3i2.80

Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) (2nd ed., Vol. 1). Erlangga.

Soemardi, B. W., & Kusumawardani, R. G. (2010). Studi Praktek Estimasi Biaya Tidak Langsung Pada Proyek Konstruksi. Konferensi Nasional Teknik Sipil, 4, 2–3.

Wohon, F. Y., Mandagi, R. J. M., & Pratasis, P. (2015). Analisa Pengaruh Percepatan Durasi pada Biaya Proyek Menggunakan Program Microsoft Project 2013 (Studi Kasus: Pembangunan Gereja GMIM Syaloom Karombasan). Jurnal Sipil Statik, 3(2).

Published

2023-03-07